Project Process

This sample construction schedule can provide you with an idea of what to expect when building a modular home.

Step 4: Site Preparation

  1. Foundations and Footings are Completed
  2. Foundation is Square and Level
  3. Foundation and Footings have passed Inspection
  4. Obstacles for Crane and Transporters have been Removed
  5. Access Route for Crane and Transporters is planned
  6. Crane Pad is Ready and Firm
  7. Set Crew and Crane Schedules are Confirmed
  8. Bulldozer and Operator Scheduled and Confirmed
  9. Utility Crews have been Scheduled for Turn-off / Turn-on (if applicable)
  10. Weather Forecast for Set Day looks Adequate

Payment for Delivery Day Confirmed and Available